Union Bridge Construction Schedule (Rt. 3 between Ashland and Bridgewater)

June 13, 2025
  • May 19 to July 15, 2025 – site mobilization and trestle installation
  • July 15 to August 15, 2025 – stone ramp and cofferdam construction
  • August 15 to November 30, 2025 – pier 7 shoring and repair work
  • November 30, 2025 to late Summer 2026 – superstructure work and access retention-trestle, cofferdam, and stone causeway remain in place and maintained until all bridge deck and truss work completed
  • Late Summer to Fall 2026 – removal of trestle, cofferdam, and stone causeway